Hiwinui

WetLand Drainage

Project Overview

Alistair Davis faced persistent drainage issues in his orchard, preventing Feijoa trees from thriving. The wet ground beneath the trees, ineffective previous drainage, and a low-lying area falling in the wrong direction contributed to poor growing conditions. Additionally, an overgrown road drain and a blocked culvert exacerbated water retention in the area.

Challenges & Site Considerations

  • Limited access due to fencing, tree stumps, and an abandoned shed.
  • Presence of a water line requiring careful excavation.
  • A main telecommunications cable to trench over without damage.
  • Blocked road culvert filled with debris and mud, restricting water flow.

Solution & Executi

To resolve these issues, a comprehensive drainage system was implemented, including:

1. Site Preparation & Access: 

  • Demolished and removed the abandoned shed. 
  • Removed a section of fencing for equipment access.
  • Cleared agapanthus obstructing the road drain.

2. Drainage System Installation:

  • Excavated and strategically trenched 120m of drainage to direct water flow effectively.
  • Used 110mm punched drain flow pipe with a filter sock, laid in a 450mm wide trench graded at 1:100 (1%).
  • Surrounded the pipe with 14-19mm washed drainage stone, covered with filter cloth, then overlaid with topsoil.
  • Access points installed at all junction
  • Installed clean-out points at the end of each drainage run for future maintenance.

3. Land Regrading & Replanting Preparation:

  • Imported and laid 50m³ of screened topsoil over the affected area.
  • Raised up the low-lying area and built a planting bund for new Feijoa trees (to be planted by the client).

4. Final Site Restoration: 

  • Reinstated the fence after completion.
  • Burned and buried tree stumps, shed remains, and fence debris on-site.
  • Reshaped the drain and cleared the road culvert to restore proper water flow.
Location:

Private Orchard


Client:

Alistair Davis


Category:

Drainage


Equipment Used:
  • 4T excavator
  • 1.5T excavator
  • 2T skid steer
  • 6-ton dump truck
  • 1-ton off-road dump truck
  • Laser Level
  • Various hand tools